When building an assembly line, different suppliers are employed for the purchase of various software and hardware. The engineers question the compatibility of the software package managing the movement of the assembly line with another one managing the movement of one of the overhead lines feeding the assembly line. They have gone through the probability and impact analysis to determine the severity of this particular risk of incompatibility between these two software packages. Their assessments are as follows: The probability the risk of incompatibility will happen is estimated to be 0.35. Quality reduction unacceptable to the client. Functionality reduction unacceptable to the client. An overall project slippage of 25% is expected. A 25% increase in the associated cost is estimated. How would you classify the severity of this particular risk?