A project to remodel a bathroom has the following activities. Build in Excel showing prdecessors (20 points).
Activity Duration Predecessors
A 2 months—
B 4 months—
C 4 months—
D 1 month A
E 5 months B
F 2 months B, C
G 1 month C
H 3 months E, F, G
I 2 months D, E
J 2 months G, H