a. Draw an appropriate diagram and calculate the critical path and critical time duration for a project consisting of these activities (10 Marks)
A – 5 B – 4 C A 3 D A 4 E A 6 F B,C 4 G D 5 H D,E 6 I F 6 J G,H 4
b. As the project manager you have been told to reduce the overall project duration of the above project by four days. You first decide to reduce each or the tasks on the critical path by one day each, but find that is not enough. Explain why this is the case and suggest what else you would need to do to achieve the target. (5 Marks) c. What additional information would be needed to use the program evaluation and review technique (PERT) for the above project? (5 Marks)