A project has 11 activities that can be accomplished either by one person working alone or by several people working together. The activities, precedence constraints, and time estimates are given in Table below. Suppose that you have up to five people who can be assigned on any given day. A person must work full days on each activity, but the number of people working on an activity can vary from day to day.. . . . . . . . . . . . . . . .. . . . . . . . . . . .    a.   Prepare an AOA network diagram, and calculate the critical path, total slacks, and free slacks assuming that one person (independently) is working on each task.

b.  Prepare an early-start Gantt chart.

c.  Prepare a daily assignment sheet for personnel with the goal of finishing the project in the minimum amount of time.

d.  Prepare a daily assignment sheet to “best” balance the workforce assigned to the project.

e.  By how many days could the project be compressed if unlimited personnel resources were available?

  • attachment

    IMG_20200705_012803.jpg

Found something interesting ?

• On-time delivery guarantee
• PhD-level professional writers
• Free Plagiarism Report

• 100% money-back guarantee
• Absolute Privacy & Confidentiality
• High Quality custom-written papers

Related Model Questions

Feel free to peruse our college and university model questions. If any our our assignment tasks interests you, click to place your order. Every paper is written by our professional essay writers from scratch to avoid plagiarism. We guarantee highest quality of work besides delivering your paper on time.

Grab your Discount!

25% Coupon Code: SAVE25
get 25% !!