Your project to deliver a product has five activities, each with a finish-to-start relationship. Project baseline information is presented below indicating the planned schedule and budgeted cost of each activity.

Baseline

Activity Name Start

(Baseline)

Finish

(Baseline)

Cost

(Baseline)

Product 6/2/14 5/25/15  
   Requirements 6/2/14 8/22/14 60,000.00
   Design 8/25/14 11/14/14   90,000.00
   Build 11/17/14 3/20/15 120,000.00
   Test 3/23/15 5/22/15 50,000.00
   Release 5/25/15 5/25/15 0.00

 

You have to report project status as of January 30, 2015. The associated schedule and cost information is provided below. Assume: (1) a five-day work week; and (2) a constant resource loading (i.e., the rate of planned expenditures is constant over the duration of each activity).

Actual

Activity Name % Complete Start

(Actual)

Finish

(Actual)

Cost

(Actual)

Product   6/2/14 NA  
   Requirements 100 6/2/14 8/30/14 68,000
   Design 100 8/31/14 11/20/14 85,000
   Build 70 11/21/14 NA 110,000
   Test 0 NA NA 0
   Release 0 NA NA 0

 

Show all work. Round dollar values to the nearest dollar. Calculate all other variables to three decimal places.

  1. Earned Value Measures
    1. Calculate earned value measures for each activity and for the cumulative project as of January 30, 2015; fill in the table below:
Activity Planned Value (PV) Earned Value (EV) Actual Cost (AC)
Requirements     68,000
Design     85,000
Build     110,000
Test     0
Release     0
Entire Project      

 

  1. What is the Budget at Completion (BAC) for the project?
  1. Earned Value Performance Measures
    1. Calculate earned value performance parameters for each activity and for the cumulative project as of January 30, 2015; fill in the table below:
Activity Schedule Variance (SV) Schedule Performance Index (SPI) Cost Variance (CV) Cost Performance Index (CPI)
Requirements        
Design        
Build        
Test        
Release        
Entire Project        

 

  1. Is the project ahead of schedule, on schedule, or behind schedule? Why?
  2. Is the project over budget, under budget, or on budget? Why?
  1. Earned Value Forecasts
    1. Assuming the Cost Performance Index (CPI) remains constant for the remainder of the project:
      1. What is the Estimate at Completion (EAC)?
      2. What is the Estimate-to-Complete (ETC)?
  • How much more or less money (other than the current budgeted amount) will you need to finish the project?
  1. How much would the Cost Performance Index (CPI) have to change in order to complete the project within the original budget?

 

 

Found something interesting ?

• On-time delivery guarantee
• PhD-level professional writers
• Free Plagiarism Report

• 100% money-back guarantee
• Absolute Privacy & Confidentiality
• High Quality custom-written papers

Related Model Questions

Feel free to peruse our college and university model questions. If any our our assignment tasks interests you, click to place your order. Every paper is written by our professional essay writers from scratch to avoid plagiarism. We guarantee highest quality of work besides delivering your paper on time.

Grab your Discount!

25% Coupon Code: SAVE25
get 25% !!