You have been assigned a very critical project. Although your team members are experts and efficient, your team performance is poor. What will you do to improve your team performance?
(a) Train them
(b) Warn them
(c) Co-locate them
(d) Punish them for poor performance
Question: 354
You have been given a task to find cost estimates for several projects, and your organization will submit its bid based on these estimates. The financial position of the organization is not very good; therefore, they tell you that they cannot invest more than 500,000 USD. They also give you a leeway of 10% on either side of it. This leeway is a part of:
(a) Organizational process assets
(b) Enterprise environmental factors
(c) Threats
(d) Opportunities