1. (a) Explain the purposes of a dummy activity in a network diagram. (2 marks)
(b) Table 1 shows the activities of a project and their durations.
Table 1
Activity Preceding Activity Duration (Days)
A – 9
B – 3
C A 8
D A 2
E A 3
F C 2
G C 6
H C 1
J B,D 4
K F,J 1
L E,H,G,K 2
M E,H 3
N L,M 4
i. Draw the project network.
ii. Determine its critical path and completion time.
iii. Calculate the total float for the non-critical chains. (18 marks)
2. a) Outline FOUR different types of stockholding casts. (4 marks)
b) i) Explain the periodic review system of inventory control.
ii) State TWO disadvantages of the periodic review system. (6 marks)
c) Explain FOUR major functions of an office. (6 marks)
d) A common trend in the office management in many large manufacturing organizations today is to set up an ‘organization and method’ (O&M) team, which is normally directly answerable to the Chief Executive Officer. Highlight FOUR responsibilities of such a team.
(4 marks)
3. a) State FOUR objectives of maintenance in a manufacturing plant. (4 marks)
b) Explain the purpose of the following documents used in planned maintenance.
i. Job card
ii. Assets (facility) register
iii. Maintenance schedule (6 marks)
c) Highlight FOUR possible reasons for selecting a certain job for work measurement.
(4 marks)
d) Explain the following terms as used in work study:
i. Work cycle
ii. Standard time
iii. Activity sampling (6 marks)
For a custom-written paper on the above topic, place your order now!
What We Offer
• On-time delivery guarantee
• PhD-level professionals
• Automatic plagiarism check
• 100% money-back guarantee
• 100% Privacy and Confidentiality
• High Quality custom-written papers