1. Consider a software development project with the following information listed in Table 1. Suppose the cost rate for one developer is $5000/week.
1)Construct the project activity network diagram using AON methodology.
2)Calculate the early, late and float times for each activity. Identify the critical path.
3)Create the resource load chart for this project based on the lately times(LS). Are there resource
overloads if the maximum of 3 developers per week available for the project? If there are, how to resolve it?