#Sales Offer!| Get upto 25% Off:

Consider the following production   of producing N identical units, which can be modelled using the repetitive project scheduling approach. The data is provided in the following table.

The minimum time buffers between two consecutive activities are given as follows: B1 ¼ 12 days; B2 ¼ 16 days; B3 ¼ 9 days; B4 ¼ 19 days. The indirect cost per day is 32 TL. (a) Draw the WP progress lines diagram and find the optimal schedule with the data given in the table above considering the minimum total cost. (b) Draw the WP progress lines diagram when the resulting schedule lasts for 142 days and report about the net gain for this schedule. (c) Find the earliest due-date and report the net gain.

Found something interesting ?

• On-time delivery guarantee
• PhD-level professional writers
• Free Plagiarism Report

• 100% money-back guarantee
• Absolute Privacy & Confidentiality
• High Quality custom-written papers

Grab your Discount!

25% Coupon Code: SAVE25
get 25% !!