The “Golden Bridge” software development project was scheduled to be completed
in about 12 months. Two to six team members were planned to work on the project at
the same time. Project progress control was based on a monthly report that would
refer to each of the 32 activities to be performed and to the components (1) risk item
management, (2) schedule, and (3) human resource utilization.
The first three monthly progress reports submitted to management did not indicate any deviation from the plan. The fourth progress report presented an unresolved
risk item that was listed in the project plan, a substantial overrun in human resource
utilization (overtime, etc.), as well as a month’s delay in the expected completion
dates for some of the activities.
a. Can you suggest possible reasons for the relatively late detection of the deviations
from the project plan?
b. For each of the above three components, describe the measures that could have
prevented the deviations and their adverse effects.