You are constructing an office building. Work has started and you are in the middle of your project. You feel that if you add one more floor to the building it will cost much less than if the client decides to add it in the future. This change, however, will lead to a change in various baselines and the project charter as well. Therefore, you discuss the

 

issue with all relevant stakeholders, and after their agreement, you process these change requests. In all of these changes, who is responsible for making this change in the project charter?

 

(a)      The project manager

(b)     The client

(c)      Management

(d)      The project management team

Found something interesting ?

• On-time delivery guarantee
• PhD-level professional writers
• Free Plagiarism Report

• 100% money-back guarantee
• Absolute Privacy & Confidentiality
• High Quality custom-written papers

Related Model Questions

Feel free to peruse our college and university model questions. If any our our assignment tasks interests you, click to place your order. Every paper is written by our professional essay writers from scratch to avoid plagiarism. We guarantee highest quality of work besides delivering your paper on time.

Grab your Discount!

25% Coupon Code: SAVE25
get 25% !!