Assessment description

This assessment requires you to write a report based on the Coca-Cola scenario provided below. You should analyse the company’s project and prepare a report (max.1500 words) which must include a project summary/background, risk plan, risk form and risk log for that particular project of the company. 

Use templates provided in the Appendix 1 (attached) to complete your report. 

Task Specifications:

o Project summary/background- description of the project and it’s goals 

o Risk plan- at least 5 risks to be identified and listed in the “Risk plan” table provided in Appendix 1 

o Risk form- 2 sample risk forms. Risks should be chosen from the 5 risks that you have identified in the risk plan 

o Risk log- for all the 5 risks that you have identified in the risk plan

o Conclusion-may include recommendation on how risk management strategies will be evaluated and how they will be executed 

• All the risks need to be relevant and identified from the given scenario, reasonable assumptions can be made

• Extra rows can be added to the template

  • Assessment tasks need to be documented in MS Word file.

    Scenario:

    Coca-Cola Amatil’s journey: Lotus Notes to BPOS

    Beverage giant moves 8000 employees to Microsoft’s hosted Business Productivity Online Suite

    Jenna Pitcher (CIO), 27 August, 2010 09:34
    Beverage company Coca-Cola Amatil (CCA) is halfway through the massive task of migrating its over 8000 employees from Lotus Notes to Microsoft’s hosted Business Productivity Online Suite, the company revealed in a presentation at Microsoft’s Tech.Ed conference on the Gold Coast this week.

    The project kicked off in March and is halfway through, according to technology services manager, Steven Meek. Each employee will receive a 5GB email account, up from 300MB. Some 69 Lotus Notes servers and 700 BlackBerrys will also be factored into the equation, along with new acquisitions.
    “We’ve made a lot of acquisitions — seven or eight companies over six years,” Meek told the audience. “That was extremely challenging — we were continually migrating people across and some companies [we] acquired were running odd systems.
    “It was kind of funny; some of the companies were using Exchange, then we moved them to Lotus Notes and now we are moving them back again. Recent acquisitions who were still on Exchange were relatively easy — it was just Exchange to Exchange migration.”

    The beverage giant’s team is half way through the rollout, which is happening incrementally. Meek’s team doesn’t just have to deal with technical challenges, however; senior levels have also put the pressure on.
    Meek’s chief information officer was asked by the CEO, for example, whether the migration could happen in two weeks. The team considered it, but the time frame was not feasible.

    “We’ve done about 4200 employees, which is about 600GB of email and five and half million emails and calendar entries,” Meeks said of the project’s current state.
    The data migration — documents, email and notes — was successful for most users but some were not so lucky. 

    “But it was quite simple to get across and tell them that it was coming. But of course some of them were quite happy not to have email,” Meek joked.

    The team brought every user’s email history over from Lotus Notes across to the cloud, a shift which changed the dynamic entirely. 
    “Even though we were moving to Outlook, we lost a lot of calendar integration,” Meek said. The project team used a master user list to keep employees from falling though the cracks and track staff deployment location and the number of BlackBerrys in the field.

    It was also important to have a quality directory, with the effort to upload the Lotus data and reconcile different sources of truth together being “significant”. Many dead accounts were found in the migration — for example, employees who had left the company years ago.

    Meek explained there was only very basic information in the staff directory — so part of the challenge was to chase down the details, enter that data in and get it right. 

    “We had to put in significant effort into reconciling user accounts in with that directory account and getting that data right. With moving into the cloud, there were some discrepancies, some people were getting other peoples email,” he said.
    Significant other issues such infrastructure and network hurdles were also encountered.
    “Network capacity planning — so that was really about, ‘yes, have we got enough bandwidth to put all that data up into the cloud at the rate we wanted?'” Meek said. “And then when it’s up there and the user logs on, do we have the bandwidth to get that to come back again?
    “One thing we did miss was our DNS. We didn’t really take into account the fact that there were session counts on the firewalls,” he said “We had a 4000 firewall limit so we reached a point where we were really stopped in our tracks — there something like 30,000 sessions on that firewall. So we did some more work with Telstra to add in some more capacity.”

    Meek encourages other enterprises that are looking at a similar migration to think about bandwidth and think about the actual capacity of the infrastructure. “We also had a bit of our challenge with quality of service policies with our network because of all the big cross traffic of our network and cell traffic,” he said.
    “Another problem that seems obvious in hindsight was installation of software. Software deployment was a challenge; we really should have deployed software earlier. They were deploying and not all of the software was on the desktops.”

    The team kicked off the project in March. To learn as much as they could, the IT department of 180 people jumped right in first in May to test out the software on them.

    The company also had non-IT ‘change champions’ across its business who volunteered to help champion the new technology. These champions were coached by the IT department and let out to cut through the negative talk about the change.
    The next step was executive-level migration to ensure senior level buy-in. 

    The executives were migrated first to placate their employees with the news that they had already gone through the migration.
    To keep the help desk from backing up with calls, floor walkers were deployed across sites. Their job was to walk around and help staff with any problems they encountered — a more personable approach than contacting the help desk.

    On a SharePoint-based intranet, the company also produced a lot of user help content that included a guide, a FAQ and to let employees know that the change was to “move forward with the times”.

    The next step will be the finalisation of the rollout — as well as the implementation of Microsoft’s Office Communication Server, which will facilitate video calling, to be bedded in next year.

For a custom-written paper on the above topic, place your order now!

What We Offer:

• On-time delivery guarantee

• PhD-level writers

• Automatic plagiarism check

• 100% money-back guarantee

• 100% Privacy and Confidentiality

• High Quality custom-written papers

Found something interesting ?

• On-time delivery guarantee
• PhD-level professional writers
• Free Plagiarism Report

• 100% money-back guarantee
• Absolute Privacy & Confidentiality
• High Quality custom-written papers

Related Model Questions

Feel free to peruse our college and university model questions. If any our our assignment tasks interests you, click to place your order. Every paper is written by our professional essay writers from scratch to avoid plagiarism. We guarantee highest quality of work besides delivering your paper on time.

Grab your Discount!

25% Coupon Code: SAVE25
get 25% !!