I need to create a WBS for the following:
23. The CyClon project team has started gathering information necessary to develop a project network -predecessor activities and activity time in days. The results of their meeting are found in the following table:
Activity Description Duration Predecessor
1. CyClon Project
2. Design 10
3. Procure prototype parts 10 2
4. fabricate parts 8 2
5. Assemble prototype 4 3,4
6. Laboratory test 7 5
7. Field test 10 6
8. adjust design 6 7
9. Order Stock Components 10 8
10. Order Custom Components 15 8
11. Assemble test 10 9,10
12. Test unit 5 11
13. Document results 3 12
1. Please create a work breakdown structure for the above.
2. Take your findings and create an appropriate Gannet Chart.
3. Reconfigure the CyClon schedule by entering the three finish-to-start lags. What impact did these lags have on the original schedule? On the amount of work required to complete the project?