Task1

Explain this term and give three reasons for this problem and explain how to tackle it using Software Engineering Principles.

Task 2
Which life cycle model would you follow for developing software for each of the following applications? Mention the reasons justifying your choice of a particular life cycle model.
1. A Game
2. A Text Editor

Task 3
Suppose you are the project manager of a software project that consists of the following activities:
Activity No.
Duration(Days)
Dependency
T1
10

T2
15
1
T3
5
1
T4
25
2
T5
31
3
T6
10
4
T7
18
4
T8
12
4,5
T9
17
5
T10
10
6,7,8
T11
5
10
T12
7
9
T13
5
11,12
Using Microsoft Project 2013, perform the following tasks:
A. Draw the Activity network representation of the project. [10 Marks]
B. Determine the critical path for the above.

Found something interesting ?

• On-time delivery guarantee
• PhD-level professional writers
• Free Plagiarism Report

• 100% money-back guarantee
• Absolute Privacy & Confidentiality
• High Quality custom-written papers

Grab your Discount!

25% Coupon Code: SAVE25
get 25% !!