#Sales Offer!| Get upto 25% Off:

Your project is complete and the product is ready to be delivered. The client inspects the deliverable and accepts it. What process is this?

 

(a)      Close procurement

 

(b)     Close project

(c)      Validate scope

(d)      Verify scope

Question: 378

You have been assigned as a project manager for an ongoing project. After joining the project, you start reviewing the project document and notice that the WBS dictionary has many discrepancies. Due to these discrepancies, which of the following will be least affected?

 

(a)      Resources required

(b)     Description of the work

(c)      Code of account identifiers

(d)      Training program for team members

Found something interesting ?

• On-time delivery guarantee
• PhD-level professional writers
• Free Plagiarism Report

• 100% money-back guarantee
• Absolute Privacy & Confidentiality
• High Quality custom-written papers

Grab your Discount!

25% Coupon Code: SAVE25
get 25% !!